Rabat Stadium developments: start of site preparation at the same time as the installation of the steel roof columns

Heba Press – follow-up

Work at Rabat Stadium continues at a rapid pace, as teams of workers work day and night, all week long, to have the stadium ready before March next year.

So far, work has progressed in some areas with some delay, such as the two corners of the stadium that served as vehicle entrances, where the construction of the first and second floors has been completed, and the process of Installation of booths in the corners of the third floor is underway shortly.

Alongside the major works, the process of preparing the ground on the site began with the digging of sites for the irrigation system, the evacuation of rainwater, the aeration of the lawn and the installation of the necessary equipment. In addition, work on the installation of roof supports, consisting of a. the formation of the steel columns continues.