Tiznit…citizens withdraw from a city after 10 years of waiting
![Tiznit…citizens withdraw from a city after 10 years of waiting](https://en.hibapress.com/wp-content/uploads/2025/01/Tiznit…citizens-withdraw-from-a-city-after-10-years-of-waiting-780x470.jpeg)
This article was automatically translated from HIBAPRESS, the Arabic version:
This article was automatically translated from HIBAPRESS, the Arabic version:
Heba Press – Abdel Latif Baraka
Many beneficiaries of the “Amalin” affordable housing project have expressed deep dissatisfaction due to the continued delay in the delivery of the apartments they benefited from more than 10 years ago, as some said they were forced to recover their financial payments after a long wait. .
Private sources revealed that the main reason for this delay is due to administrative complications related to the relationship between the Al-Omran company and the warehouse land interests, since the property on which the project was built belongs to the ‘State.
The information indicates that resolving this crisis requires taking into account the social nature of this project, particularly in light of the presence of new housing projects intended for families who will benefit from government housing assistance amounting to 10 million centimes as part of a royal program.
In this context, all the beneficiaries who contacted the concerned authorities expressed their hope for an urgent solution to this issue, expressing their hope that their sufferings will soon end and they will get their long-awaited apartments or real estate deeds.
These demands coincide with other demands from beneficiaries of previous housing projects, such as those linked to the “Bleu Ain” segment, which has passed for more than 15 years without the apartments being delivered nor the legal proceedings being carried out. completed.